Home Up

Completed Works Specialization

 

Current/Completed Consulting Works

Date

Network

Type of studies

Client

May 2010

Melbourne Airport 22/11 kV Network

Review of the existing Melbourne airport 22-kV network and simulation for various contingency for loss of one circuit, one intake transformer and loss of all intake supply with back up generators. Develop and analysis of various alternative network expansion plans to meet the expected demand. Comparison on the network security for each expansion plan and recommend the nest alternative network development plan for the next 10 years

CPG airport/ Melbourne Airport/Downer

Sep 2009

Fuji Oil 22/3.3 kV network

Technical studies on load flow, fault level and system integration for the 8.4-MVA generator to be synchronized to Power Grid at 22 kV. The studies include the simulation of network operation, fault level contribution and to meet various technical requirements specified by PG and EMA

HY M&E/Fuji Oil/GPA

Apr 2009

Grand Hyatt 6.6 kV/LV network

Technical studies on load flow, fault level and system integration for the Trigen plant 655 kW Generator to be synchronized to Power Grid Network at 6.6 kV through the LV network. The studies include the simulation of network operation for the existing 6.6 kV and LV network at Hyatt Hotel

CNA/Hyatt Hotel

Jan 2009

NUS 66/22/6.6 kV network

Supply and installation of Distribution Network Simulator. Review and simulation of the existing 66/22/6.6 kV network including load flow, fault level analysis, circuit connection scheme and propose restoration alternative to cater for the loss of any circuits. Analyze the effectiveness of alternative plans for system expansion and upgrade to meet increased load demand. Conduct in-house short course on LV and HT network.

Office of Estate and Development, National University of Singapore

May 2008 Garden By the Bay 22 kV network Technical studies on load flow, fault level and system integration of the CHP 6.6 kV generator to be synchronized to Power Grid 22 kV network CPG/National Parks Board
Apr 2008 Changi Airport 22 kV/LV network Review of earth fault protection for the LV network and investigate to the cause of frequent tripping of RCCB/ELR for Terminals 1, 2 and 3 Civil Aviation Authority of Singapore (CAAS)
Jan 2008 Changi Airport 66/22/6.6 kV network Review and simulation of the existing 66/22/6.6 kV network including load flow, fault level analysis, recommendation of circuit connection scheme, and the integration of two 66-kV intakes, simulation of circuit outage and propose restoration alternative to cater for the loss of one intake 66 kV substation, loss of interconnection circuit and transformer. Civil Aviation Authority of Singapore (CAAS)
Dec 2007 ST Microelectronics 22 kV/LV network at Ang Mio Kio Post-fault Simulation of busbar fault at main switchboard. Kurihara Kogyo
Oct 2007 Batam SMOE 22 kV/LV network Load estimation, sizing of transformer, stand-by generator and design of LV network from MSB to each FDB including voltage drop checking, short-circuit and earth-fault calculation and protection PT SMOE Indonesia (BTM)
Sep 2007 Payer Lebar Air Base 22/6.6 kV network

Develop and install artificial intelligence (AI) program for fault diagnose and supply restoration for Payer Lebar Air Base 22/6.6 kV network.  Advise on the methodology to implement the AI fault diagnosis and supply restoration to the SCADA system. Provide assistance and advise on the testing procedures and the commissioning of the system.

Cegelex/Defence Science & Technology Agency, DSTA
Aug 2007 Ang Mio Kio HUB 22 kV/LV network Design verification for the electrical system at Ang Mio Kio Hub for transformers No. 1 to No. 5., Lum Chang Building Contractors d
Mar 2007 Ang Mio Kio Hub 22 kV/LV network Investigation and checking to find out the possible causes for the bus-way fault at Ang Mio Kio Hub 2-MVA transformer LV terminal to MSW with simulation and calculation of the fault current distribution from 22 kV to LV.    Kurihara Kogyo Co
Sep 2006 Tuas Incinerator Plant 22/11 kV network Load flow, fault level and system earthing for the 24 MW Incinerator Plant at Tuas synchronizing to Power Grid CPG Consultants
Sep 2006 Linde Syngas Singapore 22/11/6 kV network

Load Transient studies for 700 kW compressor motor starting in the 22/11/6/0.4 kV network with local generator synchronizing to Power Grid

Linde Syngas
Aug 2006 Supreme Court 22 kV/LV network Investigation and checking to find out the possible causes for the bus-way fault from the 2-MVA transformer neutral to MSW at Supreme Court Ngee Cheng Electri Co
Jul 2006 ST Electronics silent Generator Identify the possible causes of intermittent failure on Silent Generator. Provide advise and on site supervision on various means of loading tests. Recommendation to eliminate any possible failure. ST Electronics (Satcom & Sensor Systems)
Nov 2005 TECH Semiconductor 22 kV network Simulation of Parallel Operation of 22 kV/LV Transformer TECH Semiconductor Singapore
May 2005 Linde Syngas Singapore 22/11/6 kV network

Load Flow and motor starting studies for the 22/11/6/0.4 kV network with local generator synchronizing to Power Grid

Linde Syngas

Sep 2004

LTA Circle Line 3, LV network

Develop and install LV design and assessment program (VipCoda)

Celegex

Apr 2004

LTA Circle line 22 kV and LV network

Develop and Install Computer-aided Tools for load flow, fault level calculation (VipCrop) and protective relay co-ordination (VipCag)

Jurong Consultants

Oct 2003

NUS 22/6.6 kV network

Load Flow analysis and Simulation of the 22 KV network and the replacing of the 6.6 kV network

National University of Singapore

Aug 2003

66 kV, 22 kV and LV network for the Changi Deep Tunnel Project

Develop and Install Computer-aided Tools for load flow, fault level calculation (VipCrop), protective relay co-ordination (VipCag) and LV design (VipCoda)

Building Systems Division ABB Industry

Jun 2003

Changi Naval base 22 kV Distribution Network

Artificial Intelligence System for Changi East 22 kV distribution network on fault diagnosis and supply restoration

CSE Systems & Engineering

Apr 2002

MSD Pharmaceutical Plant 22 kV, 6.6 kV and LV network Extension

overcurrent and earth fault relay gradings

Schneider Electric Singapore

Jun 2001

Wyeth-Ayerst Pharmaceutical plant, 22/6.6/0.4 kV network

Short-circuit, overcurrent and earth fault relay grading

Jacobs Lend Lease

Jun 2001

Wyeth-Ayerst Nutritional, 22/0.4 kV network

Short-circuit, overcurrent and earth fault relay grading

Jacobs Lend Lease

Mar 2001

NUS 22/6.6 kV network

Load flow analysis for network exoansion studies

National University of Singapore

Dec 2000

MSD Pharmaceutical Plant-22/6.6/0.4 kV network

Load flow, short-circuit, overcurrent and earth fault relay grading

Singapore Kogyo Co

Dec 2000

Exxon Singapore 22 kV, 6.6 kV and LV networks for Chemical Complex Extension

Load flow, short-circuit, overcurrent and earth fault relay grading

Kellogg Brown & Root

Jul 2000

Exxon Singapore 6.6 KV and LV networks for Chemical Complex Administration Building

Load flow, short-circuit, overcurrent and earth fault relay grading

Halliburton Far East

Sep 1999

LV network at Sentosa Cove Lock Gate

Consulting and Verification of electrical system

Keppel Engineering

Jul 1999

Seletar Sewage Treatment Works, 22/6.6/0.4 kV network

Load flow, short-circuit, overcurrent and earth fault relay grading

Kurihara Kogyo

Apr 1999

MINDEF 6.6 kV network at Changi East

Protection of un-earthed system

St Architects & Engineers

Mar 1998

IBM Storage System at Kakit Bukit 22/0.4 kV network

Short-circuit, overcurrent and earth fault relay grading

IBM SSD Singapore

Dec 1997

Kranji Sewage Treatment works 22/6.6/3.3/0.4 kV network

Load flow, short-circuit, overcurrent and earth fault relay grading

Kurihara Kogyo

Sep 1997

LV network at Bukit Timah Plaza

Verification on the methods of calculation of energy saving

Keppel Land International

Mar 1996

Hewlett Packard  480/240/120 V Distribution System

System earthing, earth fault protection and sizing of Frequency Converter

Hewlett Packard

Apr 1995

MINDEF 6.6 kV network  to Air Force flight simulator

Short circuit study and investigation of various means to increase fault level

MINDEF Lands & Estates Organization

Mar 1995

Clean-seas LV network on Pulau Sebarok

Consulting and Design of off-shore power supply system

Keppel Engineering

 

 

 

Home ] Up ]

Send mail to   cyteo@ntu.edu.sg  with questions or comments about this web site.
Last modified: 04/09/09